113th Street Apartments
VendorTask NameDurationStartFinishPredecessorsStatusComments
 Collaboration powered by Smartsheet   |   Report Abuse
1
-Rogers Landing
115d09/01/2002/08/21
2
Excavation
3d09/01/2009/03/20
3
Survey
1d09/04/2009/04/202
4
Set Foundation
4d09/07/2009/10/203
5
Pour Foundation
1d09/11/2009/11/204
6
Strip Foundation
2d09/14/2009/15/205
7
Underground Utilities
2d09/16/2009/17/206
8
Water Service
1d09/18/2009/18/207
9
Utility Inspection
1d09/21/2009/21/208
10
Backfill
1d09/22/2009/22/209
11
Drop Post and Beam Lumber Pack (AM Drop)
1d09/23/2009/23/2010
12
Post & Beam Framing
1d09/24/2009/24/2011
13
Post & Beam Plumbing
1d09/25/2009/25/2012
14
Rough in Crawl Fans
1d09/28/2009/28/2013
15
Post & Beam Inspections
1d09/29/2009/29/2014
16
Drop 1st Framing Pack
1d09/30/2009/30/2015
17
Framing
15d10/01/2010/21/2016
18
Truss Delivery
1d10/22/2010/22/2017
19
Framing Shear Inspection
1d10/23/2010/23/2018
20
Exterior Clean
1d10/23/2010/23/2019SS
21
Roofing
5d10/26/2010/30/2019
22
Prelim Insulation
1d10/29/2010/29/2021FS -2d
23
Plumbing Top-out
3d10/30/2011/03/2022
24
HVAC Venting
3d11/04/2011/06/2023
25
Pre Rock Tubs
1d11/02/2011/02/2023FS -2d
26
Pre Rock Inspection
1d11/02/2011/02/2025FS -1d
27
Plumbing Top out Inspection
1d11/04/2011/04/2023
28
House Wrap
2d11/04/2011/05/2023
29
Install Windows
1d11/06/2011/06/2028
30
Deliver Exterior Doors
1d11/06/2011/06/2028
31
Set Exterior Doors
1d11/09/2011/09/2030
32
Install Construction Alarm System
1d11/09/2011/09/2024
33
Electrical Rough
3d11/09/2011/11/2024
34
Dry Down
1d11/12/2011/12/2033
35
Install Siding
7d11/11/2011/19/2033FS -1d
36
Install Gutters
1d11/02/2011/02/2021
37
Framing Pickup
1d11/12/2011/12/2033
38
Rough Inspections
5d11/13/2011/19/2034
39
Insulate Walls
1d11/20/2011/20/2035
40
Insulation Inspection
1d11/23/2011/23/2039
41
Order Appliances
1d11/24/2011/24/2040
42
Stock Drywall
1d11/24/2011/24/2040
43
Nail and Tape Drywall
10d11/25/2012/08/2042
44
Heat to Units
1d11/25/2011/25/2042
45
Exterior Flatwork
3d12/09/2012/11/2043
46
Install Garage Doors
1d12/11/2012/11/2047FS +1d
47
Spray Texture
1d12/09/2012/09/2043
48
Blow Attic Insulation
1d12/14/2012/14/2046
49
Exterior Paint
3d11/25/2011/27/2042
50
Deliver Millwork
1d12/10/2012/10/2047
51
Install Millwork
5d12/11/2012/17/2050
52
Caulk and T/U Drywall
1d12/18/2012/18/2051
53
Fine Grading
1d12/21/2012/21/2045FS +5d
54
Landscaping
7d12/22/2012/30/2053
55
Interior Painter
6d12/21/2012/28/2052
56
Cabinet Install
2d12/29/2012/30/2055
57
Hard Surfaces
7d12/31/2001/08/2156
58
Install Vinyl Floors
1d12/31/2012/31/2057SS
59
Measure Mirrors
1d01/11/2101/11/2157
60
Finish Plumbing
2d01/11/2101/12/2157
61
Deliver Minor Appliances
1d01/13/2101/13/2160
62
Finish Electrical
2d01/14/2101/15/2161
63
Hookup Microwaves
1d01/18/2101/18/2162
64
Carpet
2d01/19/2101/20/2163
65
Deliver Hardware
1d01/19/2101/19/2163
66
Knob out/2nd Base
1d01/20/2101/20/2165
67
Install Mirrors
1d01/21/2101/21/2166
68
Closet Shelving
1d01/21/2101/21/2166
69
Paint 2nd Base
1d01/22/2101/22/2168
70
Deliver Major Appliances
1d01/25/2101/25/2169
71
Final Inspections
3d01/26/2101/28/2170
72
Interior Final Clean
1d01/29/2101/29/2171
73
Notice of Completion
1d01/29/2101/29/2171
74
Install Screens/Lock and Slide
1d02/01/2102/01/2172
75
Super Punch
5d02/02/2102/08/2174
76
Drywall Punch
1d02/02/2102/02/2175SS
77
Painting Touch Up
1d02/03/2102/03/2176
78
Spiff Clean
1d02/04/2102/04/2177
79
+Sales