Utica Schedule
TaskState DateEnd DateBaseline StartBaseline FinishVariancePredecessorsDuration
 Collaboration powered by Smartsheet   |   Report Abuse
1
Sign Grant Contract with State
08/01/2210/31/2208/01/2210/31/22-1d66d
2
-Purchase Expansion Property
08/01/2201/02/2308/01/2212/31/22-1d111d
3
Appraisal
08/01/2209/30/2208/01/2209/30/22-1d45d
4
Phase 1
08/01/2209/30/2208/01/2209/30/22-1d45d
5
Open/Close Escrow
08/01/2201/02/2308/01/2212/31/22-1d111d
6
-Site Prep
11/15/2207/31/2308/01/2207/30/23-1d185d
7
Contract with Corp
11/15/2201/02/2311/15/2212/31/22-1d35d
8
Vegetation Removal
04/01/2307/31/2304/01/2307/30/23-1d87d
9
Project Signage
04/15/2306/15/2304/15/2306/15/23-1d45d
10
-Hire Contractors
01/01/2305/30/2308/01/2205/30/23-1d108d
11
RFP/Award Playground
01/01/2305/30/2301/01/2305/30/23-1d108d
12
RFP/Award Bathrooms
02/01/2305/01/2302/01/2304/30/23-1d64d
13
RFP/Award Design and Construction
01/01/2305/30/2301/01/2305/30/23-1d108d
14
-Preliminary Design
04/01/2303/22/2404/15/2302/28/24-18d256d
15
Geotechnical Study
09/01/2303/22/2409/01/2312/31/23-60d146d
16
Prelim Design Team
04/01/2303/22/2404/01/2302/28/24-18d256d
17
Stakeholder Committee formed
08/01/2310/02/2308/01/2309/30/23-1d45d
18
Draft Design - Playground
09/20/2310/31/2309/20/2310/31/23-1d30d
19
DD Playground +
11/01/2301/01/2411/01/2312/31/23-1d44d
20
Remaining Park
11/15/2301/31/2411/15/2301/31/24-1d56d
21
-Construction
03/15/2412/31/2403/15/2411/30/24-22d208d
22
Sitework
03/15/2412/02/2403/15/2411/30/24-1d187d
23
Structures
05/01/2409/30/2405/01/2409/30/24-1d109d
24
Complete and Commission
11/01/2412/02/2411/01/2411/30/24-1d22d
25
Closeout
12/01/2412/31/2412/01/2412/31/24-1d23d