| 1 | Chris + Megan Matthews | Welcome: | ||
| 2 | 24019 | Job #: | ||
| 3 | Type: | Address: | City: | Style: |
| 4 | Add | Reno (Permits) | 9715 NE 198th St | Bothell | |
| 5 | Phone: | Email: | Permit # | Budget: |
| 6 | 520-391-5682 | cmathews@uw.edu// chrisfm9715@gmail.com//@uw.edu | ||
| 7 | Service | Notes | Status | Your Delivery |
| 8 | STEP 2: VISUALIZE | STEP 2 - IN PROGRESS | ||
| 9 | ex: City Guidelines | |||
| 10 | visuals | 4/28 Plan Mv4.1 is approved as noted to move foward with engaging builders for ROM pricing in tandem with the development of the permit drawings. (see attchment sketch in design journal) | y. Step Complete | |
| 11 | Scope Snapshot | |||
| 12 | STEP 3: DETAILS | Initial development of permit drwings is in process | STEP 2 - IN PROGRESS | |
| 13 | Permit Drawings | .25 QA / Detail Check | ||
| 14 | Shopping List | |||
| 15 | Detailed Design | 10.08.25 Met with owner - proceed with interior as necessary for bid while permit work proceeds. Vanity/Tub views of all baths sitting room fireplace sitting room screen wall behind couch butler pantry fridge wall of kitchen | .09 QA / Constraint Check | 12/05/25 |
| 16 | Permit Services | 05.20 Update: CURRENT CITY OF BOTHELL REVIEW TIMES: 1st Review: 6 weeks 2nd Review: 2-3 weeks Realistically: 3-6 months. Your guess is as good as mine. :) Permit application has been started on MyBuildingPermit to determine what plans and documents are required for submittal. Once design is finalized, we will verify what we need for drainage to see if we need to bring a civil engineer on board. | .22 Formwork | 01/27/26 |
| 17 | Bid | .00 Pending Approval | ||
| 18 | STEP 4: BUILD | "We love it when a plan comes together" We are not a construction company, but we don't consider a project complete until the build is finished. We provide services that support the build step. | x. Future Scope | |
| 19 | Build | I would like to have a projected Build StartDate by next step date. | x. Future Scope | |
| 20 | Purchasing | x. Future Scop | ||
| 21 | STEP 1: START | LET'S GO! | y. Step Complete | |
| 22 | Current | Any further field verification required will be completed and tracked in field verification task of STEP 3. | y. Step Complete | |