| 1 | | Craig | 3 | 31130(06) | GUY - Brad | Br 53 Coal Creek (federal) | Right of Way | Environmental studies started 8/5/2025 | ODOT in-house | | GUY | | | | | $50,000 | | | |
| 2 | | Craig | 3 | 31130(07) | GUY - Brad | Br 53 Coal Creek (federal) | Utilities | | ODOT in-house | | GUY | | | | | $50,000 | | | |
| 3 | | Craig | 2 | 36109(06) | GUY - Aaron | LWC Russell Creek NS 4420 (NO fed) | Right of Way | Environmental at USFWS for review as of 2/11/2026 | Checklist method - Stantec | | | | | | | $50,000 | | | |
| 4 | | Craig | 2 | 36109(07) | GUY - Aaron | LWC Russell Creek NS 4420 (NO fed) | Utilities | | Checklist method - Stantec | | | | | | | $50,000 | | | |
| 5 | | Craig | 3 | 38499(05) | GUY | E 330Rd Re-alignment (Ketchum Airport) | Engineering | Engineering contracting underway; Funding agreement finished. NTP issued 4/8/26 | | | | | | | | $275,000 | | | |
| 6 | | Craig | 1 | 30448(04) | GUY - Aaron | Br 27 Big (Pretty) Creek - (Federal - hist br) | Construction | R/W Underway - design changes underway; 404 permit submitted to ODOT 10/6/2025.Olsson working 404. 4 of 9 parcels secured | Kleinfelder | 8/2025 | GUY | | | | $1,727,101 | $997,899 | | | |
| 7 | | Craig | 3 | 31130(04) | GUY - Brad | Br 53 Coal Creek (federal) | Construction | Environmental studies started 8/5/2025 | ODOT in-house | | GUY | | | | $1,056,000 | $264,000 | | | |
| 8 | | Craig | 1 | 31133(04) | GUY - Aaron | Br 62 White Creek (Tribal TTBP grant) | Construction | (7-25-2025 CN to provide PE funding thru TTBP grant), Tribal invoice and Supplement sent to Commissioner, RW plans submitted 10/15. 60% PIH held 12/16. Encumbrance requested for 110K on 3/5. R/W NTP on 4/17 | ODOT in-house - ETC March 26 | 4/7/26 | GUY | | | | $30,000 | $10,000 | | $1,360,000 | |
| 9 | | Craig | 1 | 32119(04) | GUY - Aaron | Br 61A Unnamed Creek (Tribal TTBP grant) | Construction | R/W given NTP 12/11/25. (7-25-2025 CN to provide PE funding thru TTBP grant) | Kleinfelder | 12/8/2025 | GUY | | | | $20,000 | $20,000 | | $940,000 | |
| 10 | | Craig | 1 | 32120(05) | GUY - Olga | Br 29 Unnamed Creek | Engineering | | | | | | | | | $250,000 | | | |
| 11 | | Craig | 3 | 32124(05) | | Br 112 Rock Creek | Engineering | | | | | | | | | $250,000 | | | |
| 12 | | Craig | 2 | 32125(05) | | NS 4450 LWC Russell Creek (Yost) | Engineering | | | | | | | | | $250,000 | | | |
| 13 | | Craig | 2 | 36109(04) | GUY - Olga | LWC Russell Creek NS 4420 (NO fed) | Construction | Environmental at USFWS for review as of 2/11/2026 | Checklist method - Stantec | | | | | | | $1,500,000 | | | |
| 14 | | Craig | 3 | 38499(06) | GUY | E 330 Rd Re-Alignment (Ketchum Airport) | Right of Way | Engineering contracting underway,NTP issued 4/8/26 | | | | | | | | $50,000 | | | |
| 15 | | Craig | 3 | 38499(07) | GUY | E 330 Rd Re-Alignment (Ketchum Airport) | Utilities | | | | | | | | | $50,000 | | | |
| 16 | | Craig | 1 | 32126(05) | | Br 24 E Fork Big Creek | Engineering | | | | | | | | | $250,000 | | | |
| 17 | | Craig | 3 | 38499(04) | GUY | E 330Rd Re-alignment (Ketchum Airport) | Construction | Engineering contracting underway,NTP issued 4/8/26 | | | | | | | | $1,365,000 | | | |
| 18 | | Craig | 1 | 32120(06) | GUY - Olga | Br 29 Unnamed Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 19 | | Craig | 1 | 32120(07) | GUY - Olga | Br 29 Unnamed Creek | Utilities | | | | | | | | | $50,000 | | | |
| 20 | | Craig | 3 | 32124(06) | | Br 112 Rock Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 21 | | Craig | 3 | 32124(07) | | Br 112 Rock Creek | Utilities | | | | | | | | | $50,000 | | | |
| 22 | | Craig | 2 | 32125(06) | | NS 4450 LWC Russell Creek (Yost) | Right of Way | | | | | | | | | $50,000 | | | |
| 23 | | Craig | 2 | 32125(07) | | NS 4450 LWC Russell Creek (Yost) | Utilities | | | | | | | | | $60,000 | | | |
| 24 | | Creek | 3 | 30474(04) | GUY - Aaron | Br 257 Deep Fork River (Federal -Tribal-TTP) | Construction | Plans ready for construction; 404 issue - mitigation needed; supplement for mitigation and credits; supplement submitted - with CA's office | Kleinfelder; Switchgrass (prelim mitigation) | 5/25/2021 - requested re-eval on 1/20/26 | GUY | Nov 2024 | 404 submitted in May 2023 | | $20,000 | $20,000 | | $1,502,740 | |
| 25 | | Creek | 3 | 32295(04) | GUY - Brad | Br 254 Little Deep Fork Creek (Federal-TTPB grant program) | Construction | R/W Acquisition underway: only 1 of 4 secured as of 3/31/25; utility coordination meeting with utility owners on 12/12. Supplement #1 submitted to CA on 12/18/25 | Hudson Prince | 7/14/25 | GUY | | | | $20,000 | $20,000 | | $2,292,000 | |
| 26 | | Creek | 1 | 36112(06) | Kellogg | Br 116 N37700 Unnamed (Federal) | Right of Way | 30% plans submitted, 30% PIH conducted 11/18; submitted NEPA docs to environmental on 11/24/25, NEPA Kickoff 1/28/26 | Kleinfielder | | | | | | | $50,000 | | | |
| 27 | | Creek | 1 | 36112(07) | Kellogg | Br 116 N37700 Unnamed (Federal) | Utilities | | | | | | | | | $50,000 | | | |
| 28 | | Creek | 1 | 36110(04) | Kellogg | Br 191 N3800 Unnamed Creek (Federal - maj collector) | Construction | 60% PIH 3/23/26 ; submitted NEPA docs to environmental 10/15/25. Need to increase both R/W and Utilities to 90k | ODOT in House - ETC April 2026 | | | | | | $770,000 | $1,200,000 | | | |
| 29 | | Creek | 1 | 36112(04) | Kellogg | Br 116 N37700 Unnamed (Federal) | Construction | 30% plans submitted, 30% PIH conducted 11/18; submitted NEPA docs to environmental on 11/24/25, NEPA Kickoff held 1/28/26, 60% PIH held 4/9/26 | Kleinfielder | | | | | $280,000 | $559,650 | $900,350 | | | |
| 30 | | Creek | 2 | 36113(06) | GUY - Aaron | BR 9 N3697 Unnamed, Br 12 N3697 Unnamed (Federal - fed lands) | Right of Way | 30% plans submitted, PIH 10/7/2025; NEPA submitted 11/20/25, NEPA kickoff held 2/5/26 | | | | | | | | $50,000 | | | |
| 31 | | Creek | 2 | 36113(07) | GUY - Aaron | BR 9 N3697 Unnamed, Br 12 N3697 Unnamed (Federal - fed lands) | Utilities | | | | | | | | | $50,000 | | | |
| 32 | | Creek | 3 | 36114(05) | | Br 228 E0880 West Fork Sandy Creek (Federal - 404 issue) | Engineering | | | | | | | | | $250,000 | | | |
| 33 | | Creek | 3 | 36129(05) | | Br 98 N3730 Mosquito Creek | Engineering | | | | | | | | | $250,000 | | | |
| 34 | | Creek | 2 | 36113(04) | GUY - Aaron | BR 9 N3697 Unnamed, Br 12 N3697 Unnamed (Federal - fed lands) | Construction | 30% plans submitted, PIH 10/7/2025; NEPA submitted 11/20/25, NEPA kickoff held 2/5/26 | Garver | | | | | | $1,740,064 | $1,589,936 | | | |
| 35 | | Creek | 3 | 36114(06) | | Br 228 E0880 West Fork Sandy Creek (Federal - 404 issue) | Right of Way | | | | | | | | | $50,000 | | | |
| 36 | | Creek | 3 | 36114(07) | | Br 228 E0880 West Fork Sandy Creek (Federal - 404 issue) | Utilities | | | | | | | | | $50,000 | | | |
| 37 | | Creek | 3 | 36129(06) | | Br 98 N3730 Mosquito Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 38 | | Creek | 3 | 36129(07) | | Br 98 N3730 Mosquito Creek | Utilities | | | | | | | | | $50,000 | | | |
| 39 | | Delaware | 3 | 29898(05) | | Br 95 Flint Creek | Engineering | | | | | | | | | $250,000 | | | |
| 40 | | Delaware | 1 | 30482(05) | GUY | Br 35 Trib to Whitewater Creek (Federal-TTPB-grant program) | Engineering | (7-25-2025 CN to provide $110k in PE funding thru TTBP grant) - Engineering solicitation docs to ODOT, NTP issued 4/8/26. Need Funding agreement from County | | | | | | | | $250,000 | | | |
| 41 | | Delaware | 1 | 31224(06) | GUY - Aaron | Br 30 Unnamed Creek (Federal-TTPB-grant program) | Right of Way | 30% plans submitted 9/20/2025; 30% PIH scheduled 1/21/26. NEPA kickoff meeting held 1/8/26. Supplement funding has been requested by CA | CC Env | | | | | | | $100,000 | | | |
| 42 | | Delaware | 1 | 31224(07) | GUY - Aaron | Br 30 Unnamed Creek (Federal-TTPB-grant program) | Utilities | | CC Env | | | | | | | $400,000 | | | |
| 43 | | Delaware | 3 | 32842(06) | Rose & McCrary | Br 104 Fivemile Hollow Creek (Federal - scenic river) | Right of Way | Environmental underway; PIH mtg 10/23/23; funding agreement done; need draft r/w plans; designer to submit supplemental for design change | Garver | need draft r/w plans. will receive after supplement NTP | | | | | | $75,000 | | | |
| 44 | | Delaware | 3 | 32842(07) | Rose & McCrary | Br 104 Fivemile Hollow Creek (Federal - scenic river) | Utilities | | Garver | need draft r/w plans. will receive after supplement NTP | | | | | | $175,000 | | | |
| 45 | | Delaware | 1 | 34449(06) | Crafton Tull | Br 12, 13, 14 Fly Creek (change to Fed - TTBP) | Right of Way | PIH 4/21/2025; 8/2025 change to fed funds for TTBP grant | ODOT in-house | | | | | | | $50,000 | | | |
| 46 | | Delaware | 1 | 34449(07) | Crafton Tull | Br 12, 13, 14 Fly Creek (change to Fed - TTBP) | Utilities | | ODOT in-house | | | | | | | $52,000 | | | |
| 47 | | Delaware | 2 | 34450(04) | GUY - Aaron | Br 57 Beaty Creek (Federal-TTPB-grant program) | Construction | NEPA Est to complete April 2026. Stantec waiting for 106 to complete NEPA; 50k encumbrance requested on 3/9/26 | Stantec | | GUY | | | | $20,000 | $30,000 | | $1,705,000 | |
| 48 | | Delaware | 1 | 38498(05) | GUY | E 330 Rd Realignment, 1.5 Mi E of US-59 (Stand Waite Rd) | Engineering | Engineering selection docs to ODOT, NTP issued 4/8/26, funding agreement sent to county for signatures | | | | | | | | $250,000 | | | |
| 49 | | Delaware | 2 | 31230(06) | GUY - Aaron | Br 37 Whitewater Creek (Federal-TTPB-grant program) | Right of Way | NEPA underway. 60% PIH 3/19 | ODOT in-house | | GUY | | | | | $50,000 | | | |
| 50 | | Delaware | 2 | 31230(07) | GUY - Aaron | Br 37 Whitewater Creek (Federal-TTPB-grant program) | Utilities | | ODOT in-house | | GUY | | | | | $50,000 | | | |
| 51 | | Delaware | 3 | 38141(04) | GUY - Aaron | Br 112 Saline Creek (Fed - TTPB grant) | Construction | Prelims submitted 12-23-25; 30% PIH on 2/5/26; NEPA kickoff 3/23/26 | Garver | | GUY | | | | $20,000 | $30,000 | | $1,700,000 | |
| 52 | | Delaware | 3 | 29898(04) | | Br 95 Flint Creek | Construction | | | | | | | | | $550,000 | | | |
| 53 | | Delaware | 3 | 29898(06) | | Br 95 Flint Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 54 | | Delaware | 3 | 29898(07) | | Br 95 Flint Creek | Utilities | | | | | | | | | $50,000 | | | |
| 55 | | Delaware | 1 | 30482(06) | GUY | Br 35 Trib to Whitewater Creek (Federal-TTPB-grant program) | Right of Way | (7-25-2025 CN to provide $110k in PE funding thru TTBP grant) | | | | | | | | $50,000 | | | |
| 56 | | Delaware | 1 | 30482(07) | GUY | Br 35 Trib to Whitewater Creek (Federal-TTPB-grant program) | Utilities | | | | | | | | | $50,000 | | | |
| 57 | | Delaware | 1 | 31224(04) | GUY - Aaron | Br 30 Unnamed Creek (Federal-TTPB-grant program) | Construction | 30% plans submitted 9/20/2025; 30% PIH scheduled 1/21/26. NEPA kickoff meeting held 1/8/26, est completetion Dec 2026. Supplement funding has been requested by CA | CC Env | | | | | | $20,000 | $80,000 | | $900,000 | |
| 58 | | Delaware | 2 | 31230(04) | GUY - Aaron | Br 37 Whitewater Creek (Federal-TTPB-grant program) | Construction | NEPA underway. 60% PIH 3/19 | ODOT in-house | | GUY | | | | $500,000 | $1,620,000 | | | |
| 59 | | Delaware | 3 | 32842(04) | Rose & McCrary | Br 104 Fivemile Hollow Creek (Federal - scenic river) | Construction | Environmental underway; PIH mtg 10/23/23; funding agreement done; need draft r/w plans; designer submitted supplemental for design change | Garver | need draft r/w plans. will receive after supplement NTP | | | | | $284,000 | $986,000 | | | |
| 60 | | Delaware | 1 | 34449(04) | Crafton Tull | Br 12, 13, 14 Fly Creek (change to Fed - TTBP) | Construction | PIH 4/21/2025; 8/2025 change to fed funds for TTBP grant | ODOT in-house | | | | | | $20,000 | $1,310,000 | | $570,000 | |
| 61 | | Delaware | 2 | 36128(05) | | Br 63 Spavinaw Creek | Engineering | | | | | | | | | $650,000 | | | |
| 62 | | Delaware | 2 | 36128(06) | | Br 63 Spavinaw Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 63 | | Delaware | 2 | 36128(07) | | Br 63 Spavinaw Creek | Utilities | | | | | | | | | $50,000 | | | |
| 64 | | Delaware | 1 | 38498(06) | GUY | E 330Rd Realignment, 1.5 MI E of US-59 (Stand Waite Rd) | Right of Way | Engineering selection docs to ODOT | | | | | | | | $100,000 | | | |
| 65 | | Delaware | 1 | 38498(07) | GUY | E 330Rd Realignment, 1.5 MI E of US-59 (Stand Waite Rd) | Utilities | | | | | | | | | $250,000 | | | |
| 66 | | Delaware | 1 | 30482(04) | GUY | Br 35 Trib to Whitewater Creek (Federal-TTPB-grant program) | Construction | | | | | | | | $20,000 | $51,500 | | $643,500 | |
| 67 | | Delaware | 1 | 38498(04) | GUY | E 330Rd Realignment, 1.5 MI E of US-59 (Stand Waite Rd) | Construction | | | | | | | $100,000 | | $1,688,320 | | | |
| 68 | | Mayes | 2 | 31147(05) | Kellogg | Br 85 & 89 Creek - Sportsman Acres (Federal-TTPB-grant program) | Construction | NEPA re-eval docs submitted, R/W acquisition has started; Engr supplement submitted 11/17/25 | Able | Oct 2020; re-eval needed | Coates NTP 7/2025 | | | | $20,000 | $36,343 | | $1,800,000 | |
| 69 | | Mayes | 2 | 34456(04) | GUY - Aaron | E 520 Rd N4310 to N4320 (NO fed) | Construction | R/W underway - 6 parcels left - 404 submitted; Encumbered an add'l $203k for R/W on 3/10/26 | GUY - checklist | 1/29/2024 | Coates | | | | | $3,120,000 | | | |
| 70 | | Mayes | 1 | 28554(05) 36111(05) | Kellogg | Br 12A Pryor Creek (No federal) | Engineering | 30% on file | | | | | | | | $370,000 | | | |
| 71 | | Mayes | 1 | 36111(04) | Kellogg | Br 12A Pryor Creek (No federal) | Construction | 30% on file | | | | | | | | $1,881,600 | | | |
| 72 | | Mayes | 3 | 32202(06) | GUY | Anderson Rd | Right of Way | | | | | | | | | $1,150,000 | | | |
| 73 | | Mayes | 3 | 32202(07) | GUY | Anderson Rd | Utilities | | | | | | | | | $600,000 | | | |
| 74 | | Mayes | 1 | 36111(06) | Kellogg | Br 12A Pryor Creek (No federal) | Right of Way | 30% on file | | | | | | | | $100,000 | | | |
| 75 | | Mayes | 1 | 36111(07) | Kellogg | Br 12A Pryor Creek (No federal) | Utilities | | | | | | | | | $50,000 | | | |
| 76 | | Nowata | 1 | 34457(04) | GUY - Aaron | NS 423 Lightning Creek LWC (NO fed) | Construction | R/W acq underway -revised r/w plans & negotiations with landowners difficult; need 90% plans | GUY - checklist method | 1/29/2024 | GUY | | 12/1/2025 | | | $1,750,000 | | | |
| 77 | | Nowata | 1 | 30504(04) | GUY - Aaron | E260 Trib to Lightning LWC (NO fed) | Construction | R/W underway, 1 parcel left; 404 permit complete | Stantec | 1/29/2024 | GUY | | | | | $1,230,000 | | | |
| 78 | | Nowata | 1 | 34458(05) | | EW26 Trib to Purgatory Creek (No fed) | Engineering | | | | | | | | | $250,000 | | | |
| 79 | | Nowata | 3 | 38822(05) | | EW 2 from NS 412 0.8 mi to the East (John Deere Rd) | Engineering | | | | | | | | | $250,000 | | | |
| 80 | | Nowata | 1 | 34458(06) | | EW26 Trib to Purgatory Creek (No fed) | Right of Way | | | | | | | | | $50,000 | | | |
| 81 | | Nowata | 1 | 34458(07) | | EW26 Trib to Purgatory Creek (No fed) | Utilities | | | | | | | | | $50,000 | | | |
| 82 | | Nowata | 2 | 34459(05) | | Br 30 Trib to Hickory Creek | Engineering | | | | | | | | | $250,000 | | | |
| 83 | | Nowata | 1 | 34458(04) | | EW26 Trib to Purgatory Creek | Construction | | | | | | | | $640,000 | $160,000 | | | |
| 84 | | Nowata | 2 | 34459(06) | | Br 30 Trib to Hickory Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 85 | | Nowata | 2 | 34459(07) | | Br 30 Trib to Hickory Creek | Utilities | | | | | | | | | $50,000 | | | |
| 86 | | Nowata | 2 | 38500(05) | | Br 27 & 32 Old 169 over Hickory Creek | Engineering | | | | | | | | | $450,000 | | | |
| 87 | | Nowata | 3 | 38822(06) | | EW 2 from NS 412 0.8 mi to the East | Right of Way | | | | | | | | | $150,000 | | | |
| 88 | | Nowata | 3 | 38822(07) | | EW 2 from NS 412 0.8 mi to the East | Utilities | | | | | | | | | $550,000 | | | |
| 89 | | Osage | 3 | 29416(04) | GUY - Aaron | Br 220 Claremore Creek (Tribal - TTBP grant) | Construction | R/W acquisition underway - Working on URA and supplement for an additional 663K. Supplement routed for ODOT signatures on 1/20/26. Need URA back with signatures. 0 of 3 parcels secured | Enercon | done 6/15/2015 - need Re-eval (in-house) | GUY | | | | $500,000 | $32,000 | | $400,000 | |
| 90 | | Osage | 2 | 31249(04) | GUY - Aaron | Rock School Rd 100th W Ave (NO fed) | Construction | secured last file - Aug 2025 - awaiting payment; supplement for utility relo mgmt. R/E aqcuisition complete, need affidavit for LP-1 clearance | Able | 4-17-2017 need re-eval | GUY | | | | | $1,520,000 | | | |
| 91 | | Osage | 1 | 36115(06) | Kellogg | Br 86 Bird Creek 5782C (Federal - Tribal - TTBP grant) | Right of Way | 30% plans submitted 10/16/2025; 30% PIH 12/9/25; NEPA checklist sent to EPD 1/15/2026 | | | | | | | | $50,000 | | | |
| 92 | | Osage | 1 | 36115(07) | Kellogg | Br 86 Bird Creek 5782C (Federal - Tribal - TTBP grant) | Utilities | | | | | | | | | $50,000 | | | |
| 93 | | Osage | 2 | 30638(04) | GUY - Olga | 43rd St N Extension Phase 1 | Construction | R/W underway - 1 parcel left; convert environmental to federal; Need NEPA checklist to start the federal NEPA | Able | Checklist 3/29/2021- will need a new NEPA request | GUY | | | $707,143 | | $792,857 | | $2,000,000 | |
| 94 | | Osage | 3 | 34579(04) | Kellogg | Blackburn Road Embankment Repair | Construction | No ER funds; 90% plans submitted; R/W done; get it shelf ready; need FFR | Kleinfelder | Aug 2022 | Pinnacle | March 2024 | | $50,000 | | $2,990,000 | | | |
| 95 | | Osage | 1 | 36115(04) | Kellogg | Br 86 Bird Creek 5782C (Federal - Tribal - TTBP grant) | Construction | 30% plans submitted 10/16/2025; 30% PIH 12/9/25; NEPA checklist sent to EPD 1/15/2026; NEPA kickoff held 4/8/26 | | | | | | | $406,070 | $1,693,930 | | $600,000 | |
| 96 | | Osage | 2 | 30508(04) | GUY | 52nd W Ave & 133rd St N Intersection | Construction | | | | | | | $857,143 | | $42,857 | | $800,000 | |
| 97 | | Osage | 3 | 30548(04) | GUY | Br 210 Sycamore Creek | Construction | | | | | | | | $72,800 | $227,200 | | $500,000 | |
| 98 | | Ottawa | 1 | 38509(06) | GUY - Aaron | C St, D St, Commerce Drainage & Reconstruction (D Furnas Blvd; Mickey Mantle) | Right of Way | Working on preliminary plans | | | | | | | | $500,000 | | | |
| 99 | | Ottawa | 1 | 38509(07) | GUY - Aaron | C St, D St, Commerce Drainage & Reconstruction (D Furnas Blvd; Mickey Mantle) | Utilities | | | | | | | | | $500,000 | | | |
| 100 | | Pawnee | 2 | 25444(04) | M-B / ISG | Br 2 Belford Bridge (Federal, grant money) | Construction | 404 permit received 8/2025; plans are shelf-ready; Need new Tern (bird) study; Rec'd grant funding - bundled with 2 on-system projects. June 2027 letting due to schedule of on-system projects. | ODOT | done | County | done | July 2025 | $857,143 | $2,206,134 | $6,736,723 | | | $9,000,000 |
| 101 | | Pawnee | 2 | 30603(05) | | E 4440 - S 35300 Rd to 35500 Rd (Maj Collector) | Engineering | | | | | | | | | $400,000 | | | |
| 102 | | Pawnee | 2 | 32156(04) | Kellogg | Br 40 Turkey Creek (Federal) (possible TTBP grant) | Construction | R/W complete, sent Affidavit to County; 90% plans submitted 12/2024; need FFR, Requested 404 docs from designer; Requested NEPA re-eval | Kleinfelder | 3/2021 | Poe | 1/14/26 | | | $960,000 | $240,000 | | | |
| 103 | | Pawnee | 1 | 39329(05) | | Br 102 Ranch Creek | Engineering | | | | | | | | | $150,000 | | | |
| 104 | | Pawnee | 2 | 39325(05) | | Br 41 Turkey Creek | Engineering | | | | | | | | | $150,000 | | | |
| 105 | | Pawnee | 2 | 30603(06) | | E 4440 - S 35300 Rd to 35500 Rd (Maj Collector) | Right of Way | | | | | | | | | $150,000 | | | |
| 106 | | Pawnee | 2 | 30603(07) | | E 4440 - S 35300 Rd to 35500 Rd (Maj Collector) | Utilities | | | | | | | | | $400,000 | | | |
| 107 | | Pawnee | 1 | 32157(04) | Kellogg | Br 79 Panther Creek | Construction | 60% plans are done; R/W selection done; need R/W proposal & contract | Hudson Prince | 10/10/2025 | GUY | | | $577,143 | $100,000 | $382,857 | | | |
| 108 | | Pawnee | 1 | 39329(06) | | Br 102 Ranch Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 109 | | Pawnee | 1 | 39329(07) | | Br 102 Ranch Creek | Utilities | | | | | | | | | $50,000 | | | |
| 110 | | Pawnee | 2 | 39325(06) | | Br 41 Turkey Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 111 | | Pawnee | 2 | 39325(07) | | Br 41 Turkey Creek | Utilities | | | | | | | | | $50,000 | | | |
| 112 | | Pawnee | 2 | 30603(04) | | E 4440 - S 35300 Rd to 35500 Rd (Maj Collector) | Construction | | | | | | | | $500,000 | $4,000,000 | | | |
| 113 | | Pawnee | 1 | 39329(05) | | Br 102 Ranch Creek | Construction | | | | | | | | $200,000 | $800,000 | | | |
| 114 | | Pawnee | 2 | 39325(04) | | Br 41 Turkey Creek | Construction | | | | | | | | $200,000 | $600,000 | | | |
| 115 | | Rogers | 1 | 28601(06) | Kellogg | Br 75 Little Dog Creek (possible TTBP grant) | Right of Way | | | | | | | | | $50,000 | | | |
| 116 | | Rogers | 1 | 28601(07) | Kellogg | Br 75 Little Dog Creek (possible TTBP grant) | Utilities | | | | | | | | | $65,000 | | | |
| 117 | | Rogers | 1 | 28601(04) | Kellogg | Br 75 Little Dog Creek (possible TTBP grant) | Construction | | | | | | | | $20,000 | $90,000 | | $990,000 | |
| 118 | | Tulsa | 1 | 38503(05) | Kimley-Horn | Br 21 156th St N over Cherry Ck, At Mingo Rd | Engineering | Supplement | | | | | | | | $352,375 | | | |
| 119 | | Tulsa | 2 | 25487(04) | Olsson | Dip Creek Road (NO fed) | Construction | 90% plans submitted; 8/27/25 add $112k util and $25k R/W funds, funds are encumbered. Need to add 40k to R/W encumbrance; R/W submittal to Kenerson 1/13/2026; FFR 3/11/26 | Olsson | 1/12/26 | WSB | | | | | $1,300,000 | | | |
| 120 | | Tulsa | 3 | 29345(04) | Garver | 101st - Mingo to Garnett (INCOG STP) (Includes Intersection) | Construction | FEMA has updated the Floodway/Floodplain since that 404 was submitted and the proposed design no longer meets a no rise condition. will updated 404 after design changes; R/W - 2 parcels remain (1 to go to condemnation); 4/12/26 - increase construction by $4M due to engr est higher than program | Garver | done | WSB | | | | | $6,040,000 | | $4,660,000 | |
| 121 | | Tulsa | 1 | 30885(04) | GUY - Olga | E 51st St - 162nd to 177th & Intersection (Federal - STP INCOG) | Construction | Utility relocations are underway | Garver | 7/28/2020; re-eval needed | WSB | 1 parcel remaining as of 11/25 | | $857,143 | | $2,120,357 | | $4,672,500 | |
| 122 | | Tulsa | 3 | 33567(04) | Crafton Tull | 121st St Elwood to US-75 (Federal, Bond/SalesTax) | Construction | R/W underway - 6 parcels remain | Garver | 3/9/22 | WSB | | | | $249,033 | $250,967 | | $6,000,000 | |
| 123 | | Tulsa | 1 | 38502(06) | Kellogg | Br 019 156th St N over Horsepen Creek, 0.2 mi E of Sheridan (Add federal funds) | Right of Way | PIH 10/14/2025; NEPA underway; 60% plans submitted 1/16/2026; Need R/W agent selection | ODOT in-house ETC 3/26 | | | | | | | $50,000 | | | |
| 124 | | Tulsa | 1 | 38502(07) | Kellogg | Br 019 156th St N over Horsepen Creek, 0.2 mi E of Sheridan (Add federal funds) | Utilities | | ODOT in-house ETC 3/26 | | | | | | | $100,000 | | | |
| 125 | | Tulsa | 1 | 38504(06) | Garver | Br 049 106th St N over Bird Creek, 0.8 mi E of Peoria Ave (TTBP) | Right of Way | Submitted conceptual report and awaiting review meeting, PE meeting held 1/5, working towards 30% | | | | | | | | $50,000 | | | |
| 126 | | Tulsa | 1 | 38504(07) | Garver | Br 049 106th St N over Bird Creek, 0.8 mi E of Peoria Ave (TTBP) | Utilities | | | | | | | | | $100,000 | | | |
| 127 | | Tulsa | 1 | 38505(06) | Benham | Br 057 96th St N over Bird Creek, 0.3 mi E of Peoria (TTBP) | Right of Way | working to schedule 30% PIH | | | | | | | | $50,000 | | | |
| 128 | | Tulsa | 1 | 38505(07) | Benham | Br 057 96th St N over Bird Creek, 0.3 mi E of Peoria (TTBP) | Utilities | | | | | | | | | $100,000 | | | |
| 129 | | Tulsa | 2 | 30608(04) | GUY - Aaron | Br 231 Sand Creek | Construction | ODOT added $20k ea for R/W & Util in FY25; Engr supplement for environmental checklist method submitted | Hudson Prince | | WSB | | | | | $550,000 | | | |
| 130 | | Tulsa | 1 | 30610(04) | CEC | Br 7 Trib to Skalall Creek (TTBP) | Construction | R/W Plans submitted. submitted NEPA docs on 10/3/25. 60% PIH held on 3/17/26 | CEC | ODOT In-House | WSB | | | | $40,000 | $40,000 | | $1,780,000 | |
| 131 | | Tulsa | 1 | 31223(04) | Kellogg | Br 47 Charley Creek | Construction | 60% plans submitted | Garver | 12/11/2025 | WSB | | | | $375,627 | $524,373 | | | |
| 132 | | Tulsa | 1 | 32179(04) | Garver | Br 48 106th St N Hominy Creek (TTBP) | Construction | Have 90% Plans. Working on federal NEPA - need to have a public involvement meeting. Conversion to fed funds & TTBP grant. | Garver | checklist method done; need a full NEPA, NEPA should be complete May 2026 | WSB | | | | $20,000 | $20,000 | | $3,710,000 | |
| 133 | | Tulsa | 1 | 38502(04) | Kellogg | Br 019 156th St N over Horsepen Creek, 0.2 mi E of Sheridan (Add federal funds) | Construction | PIH 10/14/2025; NEPA underway; 60% plans submitted 1/16/2026; Need R/W agent selection | ODOT in-house ETC 3/26 | | | | | | $50,000 | $970,000 | | | |
| 134 | | Tulsa | 1 | 38506(06) | Olsson | Br 083 56th S N over Bird Creek, 0.05 mi E of Memorial | Utilities | Awaiting 30% plans | | | | | | | | $50,000 | | | |
| 135 | | Tulsa | 1 | 38506(07) | Olsson | Br 083 56th S N over Bird Creek, 0.05 mi E of Memorial | Right of Way | | | | | | | | | $100,000 | | | |
| 136 | | Tulsa | 1 | 38503(06) | Kimley-Horn | Br 021 156th St N over Cherry Creek, at Mingo Rd | Right of Way | | | | | | | | | $50,000 | | | |
| 137 | | Tulsa | 1 | 38503(07) | Kimley-Horn | Br 021 156th St N over Cherry Creek, at Mingo Rd | Utilities | | | | | | | | | $100,000 | | | |
| 138 | | Tulsa | 1 | 38504(04) | Garver | Br 049 106th St N over Bird Creek, 0.8 mi E of Peoria Ave (TTBP) | Construction | Submitted conceptual report and awaiting review meeting, PE meeting held 1/5, working towards 30% | | | | | | | $20,000 | $20,000 | | $5,660,000 | |
| 139 | | Tulsa | 1 | 38505(04) | Benham | Br 057 96th St N over Bird Creek, 0.3 mi E of Peoria (TTBP) | Construction | working to schedule 30% PIH | | | | | | | $20,000 | $20,000 | | $7,510,000 | |
| 140 | | Tulsa | 1 | 38503(04) | Kimley-Horn | Br 021 156th St N over Cherry Creek, at Mingo Rd | | Construction | | | | | | | $980,000 | $420,000 | | | |
| 141 | | Washington | 3 | 31177(04) | Kellogg | Br 146 Saunders Creek (Federal -Tribal-TTPB-grant program) | Construction | R/W complete, sent affidavit to commissioner; FFR completed 11/4 | Kleinfelder | done | Coates | | | | $20,000 | $20,000 | | $1,360,000 | |
| 142 | | Washington | 2 | 38821(06) | Kellogg | EW 11 BR# 44 Unnamed (TTBP Grant program) | Right of Way | Selection Notification sent 3/18. Need scope and fee | | | | | | | | $50,000 | | | |
| 143 | | Washington | 2 | 38821(07) | Kellogg | EW 11 BR# 44 Unnamed (TTBP Grant program) | Utilities | | | | | | | | | $50,000 | | | |
| 144 | | Washington | 2 | 38821(04) | Kellogg | EW 11 BR# 44 Unnamed (TTBP Grant program) | Construction | Selection Notification sent 3/18. Need scope and fee | | | | | | | $20,000 | $42,888 | | $900,000 | |
| 145 | | Washington | 2 | 39331(05) | | NS395 Br 86 & 87 Tribs to Caney River | Engineering | | | | | | | | | $250,000 | | | |
| 146 | | Washington | 2 | 39330(05) | | EW 24 Br 81 Fish Creek | Engineering | | | | | | | | | $250,000 | | | |
| 147 | | Washington | 2 | 39330(06) | | EW 24 Br 81 Fish Creek | Right of Way | | | | | | | | | $50,000 | | | |
| 148 | | Washington | 2 | 39330(07) | | EW 24 Br 81 Fish Creek | Utilities | | | | | | | | | $50,000 | | | |
| 149 | | Washington | 2 | 39331(06) | | NS395 Br 86 & 87 Tribs to Caney River | Right of Way | | | | | | | | | $50,000 | | | |
| 150 | | Washington | 2 | 39331(07) | | NS395 Br 86 & 87 Tribs to Caney River | Utilities | | | | | | | | | $50,000 | | | |
| 151 | | Washington | 2 | 39331(04) | | NS395 Br 86 & 87 Tribs to Caney River | Construction | | | | | | | | $1,693,334 | $2,326,666 | | | |
| 152 | | Washington | 2 | 39330(04) | | EW 24 Br 81 Fish Creek | Construction | | | | | | | | $20,000 | $2,000,000 | | | |