| _ | __ | ____ | |
| Collaboration powered by Smartsheet | Report Abuse | |||
| 1 | Type: | Address: | |
| 2 | Accessory Other | 3322 Sahalee Dr W, Sammamish, WA | |
| 3 | Service | Notes | Your Delivery |
| 4 | Danforth | Holiday Email Sent Waiting on Geotech. - Need Arborist TBD - Wild Goose Chase by CIty Code - City not clear | |
| 5 | JRNL | ||
| 6 | Current | 06/16/25 | |
| 7 | EX: Site Visit | ||
| 8 | ex: City Guidelines | 07/08/25 | |
| 9 | EX: Drafting | DRAFTING SCOPE: Existing garage walls will be demolished so we only need draw the permiter of the garge and the garage and man door openings. Existing foundation and slab will be re-used. (we will need to verify foundation size with a shovel at some point). At the existing home just draw the corner of the home. (see mark-up on drive) We will need existing exterior elevation of the house drawn. However I did not measure the existing house as the homeowner may have some floor and site plans that can help. | |
| 10 | EX: Drone | ||
| 11 | EX: Site Plan | 05/06/25 | |
| 12 | EX: Site Tech | ||
| 13 | How much $? (R O M) | Homeowners to engage with builders for pricing | |
| 14 | visuals | Visuals are complete. Any further updates to plans as necesary should be incorporated into the permit drawings. | 08/08/25 |
| 15 | BID | HOMEOWNER TASK Plans have been issued for homeowner to get final bids. | |
| 16 | DETAILED DESIGN | HOMEOWNER TASK Homeowner to schedule a time to review exterior facade modifcations with the team | |
| 17 | Landscape | ||
| 18 | FINANCE | Consultant | |
| 19 | PERMIT DRAWINGS | ||
| 20 | Arborist | ||
| 21 | Asbestos | Consultant | |
| 22 | Asbestos Abatement | ||
| 23 | Civil | Consultant | |
| 24 | Field Verifcation | ||
| 25 | Geo-tech | Consultant | |
| 26 | Septic | Consultant | |
| 27 | Structural | ||
| 28 | Surveyor | ||
| 29 | PERMIT SERVICES | Preparing Drawings for Re-Submission, Awaiting reports from client and from DOB reviews | |
| 30 | External Fees | Permit fees and consultant fees to be paid directly to consultant or city. | |
| 31 | Zoning Chart | ||
| 32 | SHOPPING LIST | List and quantites of all finish materials, fixtures and equipment required. Actualluy specifications of items will not be include unless it is required for buildling permit. | |
| 33 | STEP 4: BUILD | GC Selected Mark Kovats Sammamish Remodel 4259996996 mkovats@sammamishrcb.com Construction support services are available as needed Start Date TBD | |
| 34 | BUILD | Support the BUILD team as necessary. | |
| 35 | PURCHASING | Support the final order and deliver process as necessary. | |