Minneapolis Building Permit Fee Schedule
...
 Collaboration powered by Smartsheet   |   Report Abuse
1
The total fee for a Building Permit is determined by adding together:
Building Permit Fee + Plan Review Fee (65% x building permit fee) + MN State Surcharge (Value of Work x 0.0005) = Total Permit Fee
2
3
Construction Value*
Building Permit Fee
4
Minimum Fee-Residential or Commercial
$84.20 (does not include State Surcharge)
5
$1.00 - $500.00
$36.70 (Minimum Fee Applies)
6
$501.00 - $2,000.00
$36.70- first $500 plus $4.50 each add’l $100 and fraction thereof including $2,000
7
$2,001.00 - $25,000.00
$104.20- first $2,000 plus $20.60 each add’l $1000 and fraction thereof including $25,000
8
$25,001.00 - $50,000.00
$578.00- first $25,000 plus $14.90 each add’l $1000 and fraction thereof including $50,000
9
$50,001.00 - $100,000.00
$950.50- first $50,000 plus $10.60 each add’l $1000 and fraction thereof including $100,000
10
$100,001.00 - $500,000.00
$1,480.50- first $100,000 plus $8.40 each add’l $1000 and fraction thereof including $500,000
11
$500,001.00 - $1,000,000.00
$4,840.50- first $500,000 plus $6.90 each add’l $1000 and fraction thereof including $1,000,000
12
$1,000,001.00 and up
$8,290.50- first $1,000,000 plus $5.60 each add’l $1000 and fraction thereof
13
14
*Construction Value to be included in determining building permit valuation in accordance with building code language (1300.0160 Subp 3), bulletin 058 and Minneapolis Code of Ordinances (Title 5, Ch. 91, Article II, Section 91.220)
15
16
Detached garages
17
See Minneapolis detached garage fee schedule