1 | | | Construction (Public Works and Improvement) |
| Public Works | 6th Ave & S 19th St Railroad Crossing Improvements | Pedestrian rail crossing improvements are planned at both the 6th Avenue and S. 19th Street rail crossings. Select improvements include upgraded railroad signals, relocated vehicle railroad gates, the installation of new pedestrian railroad gates, sidewalks, curb ramps, pavement replacement, pavement markings/crosswalks, landscaping, signage and fencing. | $730,000.00 | Q3 2024 | 98465 |
2 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 24 & 35 | This street paving (maintenance) project will be completed in conjunction with capital improvements associated with the Local Improvement District program. | $2,500,000.00 | Q1 2024 | 98407 |
3 | | | Construction (Public Works and Improvement) |
| Public Works | Prairie Line Trail Phase II | This project will create a 1/3 mile long pedestrian and bike trail along the former BNSF Railway line running from 21st to 23rd. Plantings, storm water improvements, and lighting will be part of the project. | $7,275,000.00 | Q1 2024 | 98402 |
4 | | | Construction (Public Works and Improvement) |
| Public Works | S 21st St & C St Signal Project | This project will replace traffic signals and update pedestrian infrastructure. New signal assets will include signal poles, push buttons, circuitry, and conduit. Curb ramps will be updated as needed for ADA compliance. | $905,000.00 | Q2 2024 | 98402 |
5 | | | Construction (Public Works and Improvement) |
| Public Works | St Helens Ave Overlay | The project includes construction on St. Helens Avenue, from 6th Avenue to Division Avenue, including the intersection of 6th Avenue. Improvements will consist of an asphalt grind and overlay from curb face to curb face along with bulbouts at the intersections and installation of active transportation features (bike facilities and crosswalks). | $1,499,000.00 | Q1 2024 | 98402 |
6 | | | Construction (Public Works and Improvement) |
| Public Works | TPU South 17th St Court D/E Infrastructure | This project involves installing Tacoma Power utility vaults and duct banks. | $820,000.00 | Q2 2024 | 98402 |
7 | | | Construction (Public Works and Improvement) |
| Public Works | Historic Water Ditch Trail Phase IIIA | The project will increase non-motorized or active transportation access along South Tacoma Way by constructing a shared-use path between “M” St. and Sprague. Construction funding is available fourth Quarter 2023. | $7,000,000.00 | Q2 2024 | 98409 |
8 | | | Construction (Public Works and Improvement) |
| Public Works | S Cedar St Active Transportation Improvements | Marked crosswalk, pedestrian crossing advance stop bars, rectangular rapid flashing beacons, lane width reduction, road reconfiguration, median channelization/turn restrictions, ADA curb ramp retrofits, audible pedestrian signal, bicycle wayfinding (signs and markings), buffered bike lanes, green pavement markings, one-way or two-way protected bike lane, sidewalk with curb and buffer, pedestrian countdown signal, bike signal detection, bike box, engineering investigation re: speed limit & bike ramp | $1,100,000.00 | Q4 2025 | 98421 |
9 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 23 | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $3,810,630.00 | Q4 2023 | 98405/98406 |
10 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 32A | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $2,700,000.00 | Q1 2024 | 98405 |
11 | | | Construction (Public Works and Improvement) |
| Public Works | E 38th St (Portland-SR 7) Overlay | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $983,742.00 | Q2 2024 | 98404 |
12 | | | Construction (Public Works and Improvement) |
| Public Works | E 64th St Phase II | This project consists of replacing the pavement, adding bike lanes, replacing sidewalks and curb ramps to meet ADA standards, upgrading the stormwater system, upgrading the illumination system, and including LED lighting between McKinley and Portland. | $6,000,000.00 | Q2 2024 | 98404 |
13 | | | Construction (Public Works and Improvement) |
| Public Works | E Portland Ave (56-64) Overlay | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $600,000.00 | Q3 2024 | 98404 |
14 | | | Construction (Public Works and Improvement) |
| Public Works | McKinley Avenue Overlook | This project will depave and improve the overlook area along East 32nd Street and provide a useable, public greenspace for the community. Included in this project are a planted landscape area with a sidewalk pathway, interpretive signing, viewfinders, garbage cans, seating, streetlights, and defined parking spaces. This space will make use of the viewpoint and promote active transportation, improve safety and limit vehicular speeding, reduce littering, and build a cohesive sense of community. Future placemaking and arts will be incorporated throughout the project after construction is complete. | $300,000.00 | Q2 2024 | 98404 |
15 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 15 | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. Scheduled for Spring 2024 through Fall 2024. | $3,700,000.00 | Q2 2024 | 98404 |
16 | | | Construction (Public Works and Improvement) |
| Public Works | S. Yakima Sidewalk & Birney Elementary Safe Routes To School | This project consists of sidewalk improvements with an aim to provide an Americans with Disabilities Act (ADA) accessible route on S Yakima Avenue between S 67th St and S 70th St, near IDEA High School. This includes missing link sidewalk, ramp upgrades, and curb bulbs, as well as the construction of Rapid Rectangular Flashing Beacons. The work at the S Yakima Ave & 76th is aimed at providing safe routes to school for Birney Elementary School. The contractor for this project is Axum General Construction, Inc. | $514,000.00 | Q4 2023 | 98408 |
17 | | | Construction (Public Works and Improvement) |
| Public Works | Safe Routes To School: Manitou | This project will improve the school crossing by adding a raised crosswalk, Rectangular Rapid Flashing Beacons (RRFB), and lighting. The project will also add protected and buffered bike lanes and connect to the Scott Pierson Trail. This project was prioritized based on safety, equity, and connectivity metrics. | $554,000.00 | Q1 2024 | 98409 |
18 | | | Construction (Public Works and Improvement) |
| Public Works | Sheridan Arterial Improvements Project - Phase 1 | This project will rehabilitate the roadway and add curb and gutter, sidewalks on the east side and a shared use path on the west side of Sheridan Ave. from S 72nd St to S 64th St. Utility improvements include Power pole relocation, Stormwater, Sanitary Sewer and Water improvements that will occur prior to the start of roadway construction. Other amenities include landscaping, trees and retaining walls. | $4,700,000.00 | Q3 2024 | 98408 |
19 | | | Construction (Public Works and Improvement) |
| Public Works | 6th Ave Pedestrian Crossing Safety Improvements | The City was awarded a Highway Safety Improvement Program (HSIP) grant to construct needed safety improvements at selected intersections along the 6th Avenue corridor between Jackson Avenue and Grant Avenue. | $2,600,000.00 | Q2 2024 | 98405/98465/
98406/98403 |
20 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 37 | Package 37 mainly involves the construction or replacement of concrete panels, curb ramps, and conduit in various locations across Tacoma. | $3,600,000.00 | Q1 2024 | 98402/98409/
98418 |
21 | | | Construction (Public Works and Improvement) |
| Public Works | Links to Opportunity - Transit Oriented Development- Package 5 | The project will enhance the corridor along Sound Transit’s Hilltop Tacoma LINK extension route to increase accessibility and safety for residents and businesses. The scope of the improvements includes varying sidewalk color and designs, pedestrian lighting, street furniture, wayfinding signage, bicycle facilities, local art, granite inscriptions and poetry, street trees, and landscaping. The project serves one of Tacoma’s oldest historically Black neighborhoods and business districts, and the design was informed by nearly two years of grassroots outreach to the Hilltop community. Downtown: On the Go!, Hilltop Action Coalition, and Tacoma Housing Authority all assisted in the outreach effort. The final design is informed and defined by the community that it will serve and will honor the history of the corridor. | $2,000,000.00 | Q2 2024 | 98405 |
22 | | | Construction (Public Works and Improvement) |
| Public Works | S J St Bicycle Boulevard | This project will construct a two-mile bicycle boulevard on J Street from N 3rd St to S 27th St, along with improved east/west bicycle connections via 6th Avenue, S 11th Street, Earnest S Brazill St, S 17th Street, and S 18th Street, to facilitate access to Sound Transit's Tacoma Link light rail (Link) and the Hilltop Business District. | $5,000,000.00 | Q2 2024 | 98405/98409 |
23 | | | Construction (Public Works and Improvement) |
| Public Works | Pedestrian Accessibility- District 10 | This project will make improvements to and construct over 120 new ADA-compliant curb ramps, impacting 29 total intersections, that have been requested by people with disabilities and where there are identified barriers. This will improve access to between streets and sidewalks for people with mobility issues. This project will create an accessible, walkable, and equitable community within District 10. | $2,500,000.00 | Q2 2024 | Various |
24 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 18 | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $2,000,000.00 | Q1 2025 | 98465 |
25 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 40 | This street paving (maintenance) project will be completed in conjunction with capital improvements associated with the Local Improvement District program. Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $2,200,000.00 | Q1 2025 | 98406/98465 |
26 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 28 | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $1,800,000.00 | Q1 2025 | 98433 |
27 | | | Construction (Public Works and Improvement) |
| Public Works | Tacoma Spur Stadium NB/SB Ramp | The project will provide an enhanced driving surface on the Northbound and Southbound ramps to/from Interstate 705 and the Tacoma downtown area. This project will install a new cement concrete overlay on the ramp decks, new bridge deck expansion joints, and safety upgrades including a new crash attenuator at the beginning of the Northbound ramp. | $4,300,000.00 | Q1 2025 | 98402 |
28 | | | Construction (Public Works and Improvement) |
| Public Works | 38th and Cedar Street Crossing Improvements | The project will construct curb ramps, signal upgrades, and marked crosswalks at the South 38th Street and South Cedar Street intersection. Improvements will also address existing stormwater drainage concerns. | $700,000.00 | Q1 2025 | 98409 |
29 | | | Construction (Public Works and Improvement) |
| Public Works | Historic Water Ditch Trail Phase IIIB | Construction funding is available fourth Quarter 2023. The project will increase non-motorized or active transportation access along between “M” St. and South Tacoma Way by constructing a shared-use path. | $3,400,000.00 | Q1 2025 | 98409 |
30 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 30 | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $4,500,000.00 | Q1 2025 | 98409 |
31 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 32B | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $2,500,000.00 | Q2 2025 | 98405 |
32 | | | Construction (Public Works and Improvement) |
| Public Works | E Portland Ave (64-72) Overlay | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing surface. ADA curb ramp upgrades will also be made at this time if applicable. | $1,000,000.00 | Q1 2025 | 98404 |
33 | | | Construction (Public Works and Improvement) |
| Public Works | Streets Initiative Package 27 | Crews will grind out sections of pavement to make minor repairs and prepare the surface for the placement of a 2-inch layer of asphalt over the existing street surface. ADA curb ramp upgrades will also be made at this time if applicable. | $1,615,000.00 | Q2 2025 | 98404 |
34 | | | Construction (Public Works and Improvement) |
| Public Works | Safe Routes to School - Baker Middle School | This project will improve safety and walkability by adding sidewalk with curb and gutter, ADA compliant curb ramps, bulb-outs, marked crosswalks with advanced stop bars, a rectangular rapid flashing beacon, and a hybrid beacon. Speed bumps will be added to lower vehicular speed, further improving safety for all non-motorized users. Bicycle safety will be improved using green pavement bicycle crossing markings and providing a protected bicycle boulevard conversion with wayfinding signs and markings. In addition to corridor improvements, walk/bike school events, encouragement activities, and safety education classes will be provided at the end of construction. | $1,200,000.00 | Q2 2025 | 98408 |
35 | | | Construction (Public Works and Improvement) |
| Public Works | Links to Opportunity - Transit Oriented Development- Package 1 | The project will enhance the corridor along Sound Transit’s Hilltop Tacoma LINK extension route to increase accessibility and safety for residents and businesses. The scope of the improvements includes varying sidewalk color and designs, pedestrian lighting, street furniture, wayfinding signage, bicycle facilities, local art, granite inscriptions and poetry, street trees, and landscaping. The project serves one of Tacoma’s oldest historically Black neighborhoods and business districts, and the design was informed by nearly two years of grassroots outreach to the Hilltop community. Downtown: On the Go!, Hilltop Action Coalition, and Tacoma Housing Authority all assisted in the outreach effort. The final design is informed and defined by the community that it will serve and will honor the history of the corridor. | $3,500,000.00 | Q3 2025 | 98405 |
36 | | | Construction (Public Works and Improvement) |
| Public Works | S 25th St Traffic Safety Enhancements | This project is approximately 1.3 miles in length and is located on S. 25th Street between the Scott Pierson Trail and Prairie Line Trail. The project includes installing bicycle facilities such as bike lanes, shared lane markings, parking protected bike lanes, bicycle wayfinding signage, green bike lane pavement markings, bike box, bike detection, and a shared use path. It also includes installing marked crosswalks and curb ramps, and implementing leading pedestrian intervals as needed at locations along S. 25th Street approximately between the Scott Pierson Trail and Hood Street. Project includes associated ADA and utility work as needed. | $1,790,000.00 | Q2 2025 | 98405 |
37 | | | Construction (Public Works and Improvement) |
| Public Works | Foss Waterway, Site 8 Building Demolition | Provide for the demolition of the existing structure on Development Site 8 on the Thea Foss Waterway, located at 1131 Dock Street. | $300,000.00 | Q1 2024 | 98402 |
38 | | | Construction (Public Works and Improvement) |
| Public Works | Fire Communications, Sidewalk Replacement | Provide for sidewalk removal and replacements around the historic Fire Communication center, located at 415 Tacoma Avenue South. | $170,000.00 | Q2 2024 | 98402 |
39 | | | Construction (Public Works and Improvement) |
| Public Works | Tacoma Municipal Building, Exterior Repairs | Provide for cleaning and exterior repairs to the historic Tacoma Municipal Building, located at 747 Market Street. | $2,800,000.00 | Q4 2024 | 98402 |
40 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Blair Switch Project | Replace 6 railroad turnouts on the Blair Penninsula. | $930,000.00 | Q2 2024 | 98421 |
41 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Annie 1 and 2 Tracks Upgrades | Replace Several turnouts, replace ties, and Pandrol curves. | $2,800,000.00 | Q2 2024 | 98421 |
42 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Building Roof Repairs | Install new roof on TR's main building. | $350,000.00 | Q3 2024 | 98421 |
43 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Port Road and Lincoln Ave Railroad Signal Installation | Install new grade crossing signals on Port of Tacoma Road and Lincoln Ave. | $2,600,000.00 | Q4 2024 / Q1 2025 | 98421 |
44 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Battery Electric Locomotive Project | Purchase 2 Battery Electric locomotives and charging equipment. Includes installation of charging equipment as part of a construction project. | $12,700,000.00 | Q2 2024 | 98421 |
45 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Purchase of a Railroad Tamper | Purchase a tamper for railroad track maintenance activities. | $1,500,000.00 | Q3 2024 | 98421 |
46 | | | Construction (Public Works and Improvement) |
| Tacoma Rail | Battery Electric Locomotive Purchase | Purchase one Battery Electric Locomotive. | $5,500,000.00 | Q3 2024 | 98421 |
47 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Roof Replacements | Replace aging roofs at multiple CTP buildings | $2,526,596.00 | Q1 2024 | |
48 | | | Construction (Public Works and Improvement) |
| Environmental Services | SWM Full Site Channelization & Asphalt Repairs | New channelization and asphalt repair | $1,656,975.00 | Q1 2024 | |
49 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Thermophilic Digester Tower A Restoration
and Improvements (Quad A) | Rehabilitate and coat the existing concrete surfaces at the A Quad Towers at the CTP Thermophilic Digesters. Also install access hatches at ground level for maintenance access. | $991,400.00 | Q1 2024 | |
50 | | | Construction (Public Works and Improvement) |
| Environmental Services | McKinley Side Sewer Reroutes | Installation of new side sewers on McKinley Rd in order to transfer services and abandon existing main on private property. | $850,000.00 | Q2 2024 | |
51 | | | Construction (Public Works and Improvement) |
| Environmental Services | NETP Trickling Filter Upgrade | This project will construct a new trickling filter, mechanical equipment upgrades, concrete coatings, and frontage improvements at the NETP. | $9,500,000.00 | Q1 2025 | |
52 | | | Construction (Public Works and Improvement) |
| Environmental Services | Thea Foss Outfall 230A Maintenance & Repair Project | Outfall 230A put in as part of the Jefferson and Hood Project has some erosion occurring under the discharge location. This project will provide improved armoring under the outfall discharge so the City can maintain it's environmental controls for the Thea Foss Waterway | $350,000.00 | Q1 2024 | |
53 | | | Construction (Public Works and Improvement) |
| Environmental Services | SW - Various area project, N I St, S 50th, S 15th, S 42nd | Replace and upsize stormwater sewer pipes at various locations. Project will include required street restoration improvements. | $1,000,000.00 | Q1 2024 | |
54 | | | Construction (Public Works and Improvement) |
| Environmental Services | 74th & Warner Utility Project | This project will replace approximately 5,850 linear feet of 8-inch diameter public sewer main in the vicinity of S. 74th & Warner. Project includes partnership with Water and Public Works. | $3,276,000.00 | Q3 2024 | |
55 | | | Construction (Public Works and Improvement) |
| Environmental Services | NE Tacoma Vault Cleaning & Access Road - 2025 | | $250,000.00 | Q1 2025 | |
56 | | | Construction (Public Works and Improvement) |
| Environmental Services | Leach Creek Stormwater Holding Basin Modifications
& Maintenance Repairs | The objective of this project is to construct modifications to the berm area around the inlet structure, modify the alignment of the channel, modify the outlet structure, and convert a portion of the forested wetland to emergent wetland. | $2,887,433.00 | Q1 2024 | |
57 | | | Construction (Public Works and Improvement) |
| Environmental Services | SW Sewer Improvements - N 33rd and Junett | New storm sewer improvements to remove an open discharge and risk of hillside erosion above Schuester Parkway. | $700,000.00 | Q2 2024 | |
58 | | | Construction (Public Works and Improvement) |
| Environmental Services | Lincoln Ditch Maintenance | Vegetation and deposited sediment removal from approximately 2,400-lf of the Lincoln Ditch, restoring original design conditions. The project is immediately adjacent Lincoln Avenue from Milwaukee Way to Port of Tacoma Road | $400,000.00 | Q1 2025 | |
59 | | | Construction (Public Works and Improvement) |
| Environmental Services | SW CIPP 2024 | This project consists of the rehabilitation of 11,780 LF of 8-inch to 36-inch diameter stormwater mains in various Tacoma locations. | $1,500,000.00 | | |
60 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW CIPP 2024 | This project consists of rehabilitating various wastewater mains in various Tacoma locations. | $1,950,000.00 | Q1 2024 | |
61 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW CIPP 2025 | | | Q1 2025 | |
62 | | | Construction (Public Works and Improvement) |
| Environmental Services | S. 38th & Tyler | Pervious concrete replacement with standard asphalt in S. 38th St. from S Mason Ave. to S. Tyler St. | $250,000.00 | Q1 2024 | |
63 | | | Construction (Public Works and Improvement) |
| Environmental Services | On-call concrete joint repair, grouting, and epoxy
coating - 2022-23 Expense | On-Call contract for concrete restoration at various ES facilities | $450,000.00 | Q2 2024 | |
64 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW & SW Sewer Pipe Replacement -
N 8th & Pine | SW main replacement and upsizing project. | $1,330,000.00 | Q1 2024 | |
65 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW Sewer Pipe Replacement - Vicinity N 10th and Stevens | Wastewater pipe replacement project in the vicinity of the intersection of N 10th Street and N Stevens Street. Additional wastewater partial pipe replacement in alley between N 14th and N 15th Street, between N Cedar and N Junett Street. | $2,235,000.00 | Q4 2024 / Q1 2025 | |
66 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW - MH Installation South 18th | This project will install 2 manholes and roughly 30 LF of 30" storm sewer pipe. | $250,000.00 | Q2 2024 | |
67 | | | Construction (Public Works and Improvement) |
| Environmental Services | SW - N 38th and Tyler | The project will generally consist of the replacement, installation, and abandonment of 710LF of SW Mains | $480,000.00 | Q1 2024 | |
68 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW & SW 2023B WW & SW Utility Services On-Call | A 2 year contract for emergency and non-emergency spot repairs on an as-needed basis from Asset Management and Transmission. If Transmission is overloaded with side sewer repairs, it can be sent to this contract. | $650,000.00 | Q1 2024 | |
69 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Secondary Clarifier 4 & 6 | This project will replace the existing 1.5" grout layer on the bottom of the Central Treatment Plant secondary treatment tank and Epoxy inject and repair any cracks/spalls that have developed in the concrete. | $3,100,000.00 | Q1 / Q2 2024 | |
70 | | | Construction (Public Works and Improvement) |
| Environmental Services | Northshore Golf Course Ponds Maintenance | Maintenance of 3 ponds located at the Northshore Golf Course | $2,867,800.00 | Q1 2025 | |
71 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP - Bldg A HVAC replacement all Units | Replace (in-kind) the major heating, ventilation, and air conditioning (HVAC) components that service the building's occupied spaces. The equipment is beyond its useful lifespan and will begin to fail. | $1,077,000.00 | Q2 2025 | |
72 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP DAFT Odor Control System Rehab/Media Repl | " | | | |
73 | | | The existing CTP DAFT Odor Control scrubbers are nearing the end of their useful life. This project will include removal and replacement of the existing media, inspections and repairs of the scrubber tanks, air permit modifications (as needed), and overall upgrades to the system (e.g. pump replacements)." |
| $1,516,320.00 | Q2 / Q3 2025 | | Yes | | |
74 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Thermophilic Digester Tower - Quad C | Recoat the inside of each of the four tours, replace or rehabilitate the sludge distribution box, rebuild each of the mixers, recoat the handrails, replace the grating and drain piping, and repair the exterior Dryvit insulation system. | $166,400.00 | Q4 2025 | |
75 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP UNOX Tank 4113 | Rehabilitate the interior of the concrete UNOX basin. Repair all failed concrete patches, repair failed grout pads, recoat all corroded pipe supports, epoxy inject all interior and exterior cracks, rebuild all four mixer gearboxes and motors, recoat mixers with UV resistant coating. | $2,916,000.00 | Q1 2025 | |
76 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Lincoln Ave Pipe Bridge | Replace the existing debris structures with inert materials, recoat both wastewater pipelines, replace the existing air relief valves and piping expansion joints, and preform minor repairs to concrete structure. | $3,000,000.00 | Q4 2025 | |
77 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Effluent River Outfall Vault | " | | | |
78 | | | Rehabilitate and recoat the plant effluent river outfall vault. As the structure is from the Phase I upgrade, it shows signs of severe abrasion and corroded anchors. It is two chambered, and the southern chamber has all CTP primary treatment effluent flows traveling through it under normal operation." |
| $165,946.00 | Q3 2025 | | Yes | | |
79 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP Tunnel Repair | Miscellaneous structural and piping repairs within the subgrade process tunnel. | $174,960.00 | Q4 2025 | |
80 | | | Construction (Public Works and Improvement) |
| Environmental Services | AN3105 Picks Cove Pump Station Rehab | Rehabilitate and coat the wet well, replace wet well piping, pumps, and pump rails. Install venting for wet well. Rebuild or replace generator (TBD by O&M), remove abandoned control panel | $396,576.00 | Q2 2024 | |
81 | | | Construction (Public Works and Improvement) |
| Environmental Services | AN4110 Overlook Pump Station Rehab | Rehabilitate and coat the wet well, replace pumps and valves, replace VFD's. | $536,000.00 | Q2 2025 | |
82 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW & SW Tacoma Ave N 1st to N 2nd | " | | | |
83 | | | Replace the sanitary and storm system between N 1st and N 2nd" |
| $118,000.00 | Q3 2025 | | Yes | | |
84 | | | Construction (Public Works and Improvement) |
| Environmental Services | Stormwater Pond Maintenance | This project will remove sediment and vegetation in various ponds throughout NE Tacoma and W Tacoma | $288,900.00 | Q2 2025 | |
85 | | | Construction (Public Works and Improvement) |
| Environmental Services | CTP - O2 Deck Meters | Replace four 30" magnetic flow meters, four 36" influent isolation butterfly valves, four electronically actuated 36" discharge butterfly valves, Rotork valve operators, and the yard water pump discharge header pipeline. All of these assets are beyond their useful lifespan and are beginning to fail. | $1,981,509.00 | Q1 2025 | |
86 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW - E Division and E F St area | " | | | |
87 | | | This project is to replace wastewater mains" |
| $560,000.00 | Q4 2024 / Q1 2025 | | Yes | | |
88 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW - Various area Memorial Park and E K St | " | | | |
89 | | | This project is to abandoned and rebuild the system behind the old Dairy Queen at 1112 Puyallup Ave" |
| $751,000.00 | Q4 2025 | | Yes | | |
90 | | | Construction (Public Works and Improvement) |
| Environmental Services | WW - Wapato Area Main Replacement | Replace WW pipes due to poor conditions | $1,000,000.00 | Q4 2025 | |
91 | | | Construction (Public Works and Improvement) |
| Tacoma Water | CP Anode Wells | Replacing a CP anode well in the City of Enumclaw near Railroad St and Marshall Avenue. | $250,000.00 | Q2 2024 | 98022 |
92 | | | Construction (Public Works and Improvement) |
| Tacoma Water | 99th and Aqueduct/Vault/PRV replacement | The installation of a new pressure reducing valve station near 99th Street and And Aqueduct Dr E. | $175,000.00 | Q3 2024 | 98445 |
93 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Chemical Feed Lines at GRFF | This project consists of replacing all of the existing reinforced PVC lines from the chemical facility and the fluoride room at the Green River Filtration Facility (GRFF), through 17 chemical vaults (pull boxes) connected by secondary containment piping, to various injection points throughout the GRFF. | $400,000.00 | Q1 2025 | 98051 |
94 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Headworks Remodel & HVAC | Remodel of the Green River Filtration Facility Operations Center including the replacement of the existing HVAC system. | $1,300,000.00 | Q2 2024 | 98051 |
95 | | | Construction (Public Works and Improvement) |
| Tacoma Water | SI Package 40 | The project will replace approximately 4400 linear feet of 8" and 12" water distribution main and included as a part of the Street Initiative 40 road improvements. The cost estimate is for the water portion only. | $1,025,175.00 | Q3 2024 | 98406 |
96 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Curran Road - Bingham and 47th | The project will replace approximately 4100 linear feet of 8" and 10" water distribution main. | $1,700,000.00 | Q2 2024 | 98466 |
97 | | | Construction (Public Works and Improvement) |
| Tacoma Water | SI Package 28 | The project will replace approximately 2500 linear feet of 8" and 12" water distribution main and included as a part of the Street Initiative 28 road improvements. The cost estimate is for the water portion only. | $983,000.00 | Q2 2024 | 98421 |
98 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Reroof 3.5 MG Indian Hill reservoir | Replace the existing concrete reservoir roof hot mop pea gravel coating system with a new high performce coating system. | $312,000.00 | Q2 2024 | 98422 |
99 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Water Ditch Trail Ph 3B | The project will replace approximately 3000 linear feet of 8" and 12" water distribution main and included as a part of the Water Ditch Traill 3b improvements. The cost estimate is for the water portion only. | $900,000.00 | Q3 2025 | 98409 |
100 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Sheridan | The project will replace approximately 3700 linear feet of 8" and 12" water distribution main and included as a part of the Sheridan Arterial Improvements Project - Phase 1 road improvements. The cost estimate is for the water portion only. | $704,000.00 | Q3 2024 | 98408 |
101 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Streets Pkg 32 (S 12th, from Cedar to Sprague) | The project will replace approximately 3400 linear feet of 8" and 12" water distribution main and included as a part of the Street Initiative 32 road improvements. The cost estimate is for the water portion only. | $1,000,000.00 | Q2 2025 | 98405 |
102 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Ozone System Upgrade | Replacement of age Ozone equimpent components. | $3,300,000.00 | Q2 2025 | 98051 |
103 | | | Construction (Public Works and Improvement) |
| Tacoma Water | Filter Media Replenishment | A contract to add filter media in the existing filters at the Green River Filtration Facility. | $100,000.00 | Q3 2025 | 98051 |
104 | | | Architectural & Engineering (A&E) |
| Tacoma Water | Structural Concerns on Elevated Pipeline 1 Supports near the Maintenance Bridge | A professional service contract is needed to help Tacoma Water determine the extents of structural issues with pier supports on Pipeline No. 1. The supports are located alongside the maintenance bridge near the entrance to the Green River Filtration Facility. | $50,000.00 | Q3 2024 | Study |
105 | | | Architectural & Engineering (A&E) |
| Tacoma Water | Fixed Ladder & Anchor Points | A professional service contract is needed to design ladder replacements, anchorage points, verticle lifelines, and handrail at 9 Tacoma Water storage facilities. | $15,000.00 | Q3 2024 | Sudy |
106 | | | Architectural & Engineering (A&E) |
| Tacoma Water | Arc Flash Study | A professional service contract is needed to help Tacoma Water determine arch flash risks and mitigations in Water facilities. | $77,500.00 | Q1 2025 | Study |
107 | | | Architectural & Engineering (A&E) |
| Tacoma Water | Cascadia Reservoir and PS | Design and Permitting services is needed for a new reservoir and pump station to be built in the Tehaleh development. | $560,000.00 | Q4 2024 | Sudy |
108 | | | Construction (Public Works and Improvement) |
| Tacoma Power | TPU Admin Complex Storage, Parking & South Gate | An Alternative Public Works contract will be needed (drafted by third party counsel) to procure a Progressive Design-Build team to design, permit, and construct additional equipment & vehicle storage on the TPU Admin Complex. Additionally, this work will include the scope of new driveway accesses and a gatehouse along the new Access Road along the southern border of the property. | $23,925,000.00 | Q2/Q3 2024 | |
109 | | | Construction (Public Works and Improvement) |
| Tacoma Power | TPU South Service Center | An Alternative Public Works contract will be needed (drafted by third party counsel) to procure a Progressive Design-Build team to design, permit, and construct equipment & vehicle storage on the TPU South Service Center campus. | $15,700,000.00 | Q4 2024/Q1 2025 | |
110 | | | Construction (Public Works and Improvement) |
| Tacoma Power | TPU Admin Building Atrium & Entry Improvement | This project will include the replacement of the existing, historic entry curtainwall and entry. | $1,639,000.00 | Q1 2025 | |
111 | | | Architectural & Engineering (A&E) |
| Public Works | Impact Fee Study | This project will develop a proposed fee schedule, project analysis, and program implementation. | $320,000.00 | Q1 2024 | 98402 |
112 | | | | | | | |
113 | | | | | | | |
114 | | | | | | | |
115 | | | | | | | |
116 | | | | | | | |
117 | | | | | | | |
118 | | | | | | | |
119 | | | | | | | |
120 | | | | | | | |
121 | | | | ESTIMATED TOTAL VALUE | $229,761,862.00 | | |