2372 west 12 st Progress Work
DONETask NameStartFinishDurationPredecessors% CompleteAssigned ToComments
 Collaboration powered by Smartsheet   |   Report Abuse
1
-Floors
2
Basement
3
First Floor
4
Second Floor
5
-SCOPE WORK
6
Remove existing floors @ 1st & 2nd Floors.
7
Install Ceramic tile @ 1st & 2nd floor over DITRA layer.
8
Replace (10) Metal doors with Frame @ 1st and 2nd floor.
9
Upgrade 30 ceiling lights with 6" Ultra-Thin Canless LED Recessed Downlight
10
Upgrade Laundry Room Cabinets.
11
-2nd Floor
08/04/2508/22/2514.625d
12
-Flooring
08/04/2508/18/2510.625d
13
Demo existing flooring, hallways, bedrooms & living room areas
08/04/2508/05/2510h
14
Demo Doors
08/05/2508/05/252h13
15
Install DITRA membrane
08/05/2508/06/251d14
16
Install Tile
08/06/2508/13/255d15
17
Grouted Floor
08/13/2508/14/251d16
18
Install Base molding
08/14/2508/18/252d17
19
Carting away all debris for legal disposal
08/18/2508/18/251h18
20
Owner provide tile for Office space.
21
-Lights (lights)
08/18/2508/21/252.5d
22
Replace 6" recessed lights @ ceiling area ONLY (16 uints)
08/18/2508/20/252d19
23
Patch lights openings
08/20/2508/21/254h22
24
-Fire Rated Metal Doors and frame.
08/18/2508/20/252.5d
25
Replace R.H. 32x80 Bedrooms (1 units)
08/18/2508/18/254h18
26
Replace R.H. 32x80 Bedrooms (1 units)
08/19/2508/19/254h25
27
Replace R.H.30x80 Bedrooms (1 Units)
08/19/2508/19/254h26
28
Replace L.H. 30x80 Bedrooms (1 Units)
08/20/2508/20/254h27
29
Replace R.H 34x80 Entry door (1 Unit).
08/20/2508/20/254h28
30
-Stairs (units)
08/21/2508/22/251d
31
Secure handrailing, steps & Banisters
08/21/2508/21/254h23
32
Paint Railing and Banisters (oil base paint odorless)
08/21/2508/22/254h31
33
-Clean up
08/21/2508/22/251d
34
Final Clean up
08/21/2508/22/251d31
35
-1st Floor
08/22/2509/12/2514.625d
36
-Flooring
08/22/2509/08/2510.625d
37
Demo existing flooring, hallways, bedrooms & living room areas
08/22/2508/25/2510h34
38
Demo Doors
08/25/2508/26/252h37
39
Install DITRA membrane
08/26/2508/27/251d38
40
Install Tile
08/27/2509/03/255d39
41
Grouted Floor
09/03/2509/04/251d40
42
Install Base molding
09/04/2509/08/252d41
43
Carting away all debris for legal disposal
09/08/2509/08/251h42
44
Owner provide tile for Office space.
45
-Lights (lights)
09/08/2509/10/252.5d
46
Replace 6" recessed lights @ ceiling area ONLY (16 uints)
09/08/2509/10/252d43
47
Patch lights openings
09/10/2509/10/254h46
48
-Fire Rated Metal Doors and frame.
09/08/2509/10/252.5d
49
Replace R.H. 32x80 Bedrooms (1 units)
09/08/2509/08/254h42
50
Replace R.H. 32x80 Bedrooms (1 units)
09/08/2509/09/254h49
51
Replace R.H.30x80 Bedrooms (1 Units)
09/09/2509/09/254h50
52
Replace R.H. 30x80 Bedrooms (1 Units)
09/09/2509/10/254h51
53
Replace R.H 34x80 Entry door (1 Unit)
09/10/2509/10/254h52
54
-Stairs (units)
09/10/2509/11/251d
55
Secure handrailing, steps & Banisters
09/10/2509/11/254h47
56
Paint Railing and Banisters (oil base paint odorless)
09/11/2509/11/254h55
57
-Clean up
09/11/2509/12/251d
58
Final Clean up
09/11/2509/12/251d55
59
-Basement
09/11/2509/18/254.5d
60
-Laundry Room
09/11/2509/17/253.5d
61
Remove Base & Wall Cabinets.
09/11/2509/11/252h56
62
Furnish and install new Base and Wall cabinets (white Shaker)
09/12/2509/12/256h61
63
Furnish & Install stone countertop (quartz-white bianco)
09/12/2509/15/251d62
64
Furnish & install new sink with faucet
09/15/2509/16/254h63
65
Furnish & install backsplash tile.
09/16/2509/17/251d64
66
-Clean up
09/17/2509/18/251d
67
Final Clean up
09/17/2509/18/251d65