1 | | 10/03/22 | |
2 | | | Estimated Dates |
| 10/03/22 | |
3 | | | EQIP Signup Announcement (Open 30 days) |
| 10/03/22 | 11/30/22 |
4 | | | Application, FSA Eligibility, Producer Intake form Due |
| 10/03/22 | 11/30/22 |
5 | | | Screening Tools Completed |
| 10/03/22 | 11/30/22 |
6 | | | Planners work with applicants to create conservation plan |
| 10/03/22 | 02/28/23 |
7 | | | CART Assessment and Ranking |
| 03/01/23 | 03/15/23 |
8 | | | Final Cost Est., digitized Conservation Plan and maps, Job Sheets, Pre-Obligation Checklist Completed |
| 03/15/23 | 04/30/23 |
9 | | | New contracts to Area office for tech review and Program Liaison for FMMI obligation |
| 05/01/23 | 07/31/23 |
10 | | 08/28/23 | 08/28/23 |
11 | | | Upcoming Meetings |
| | |
12 | | 09/26/22 | 09/26/22 |