Bond Status Update
Project #Project NameEngineeringSurvey30%60%90%AdvertiseOpenAwardPreconstructionNoticeConstructionCloseoutColumn15Column16
 Collaboration powered by Smartsheet   |   Report Abuse
1
Project Status
2
Design PhaseBid PhaseConstruction Phase
3
Project #
Project NameEngineeringSurvey30% Plan60% Plan90% PlanAdvertiseOpenAwardPreconstructionNoticeConstructionCloseout
4
2018-01
Street Panel Replacement
5
2018-02
N. Maxwell Creek Road Improvements (B&B)
6
2018-CO.01
North Maxwell Creek Water Line Const. with N. Maxwell Rd Impr. 2018-02 (B&B)
7
2018-03
Waters Edge Park Drainage Culvert Improvements (N-S)
8
2018-04
South Murphy Road Right Turn Lane at F.M. 544 (N-S)
9
2018-05
McWhirter Road Drainage Improvements
10
2018-09
Waters Edge Park Renovation
11
2018-10
City Facilities - Renovations
12
2018-11
Heritage Parkway Landscape & Irrigation Improvements
13
2018-12
Parks and Recreation Storage Facility
14
2018-13
MAC and Central Park Consession Stand Renovations
15
2018-14
Betsy/N. Murphy Rd/McCreary Lanscape and Irrigation Improvements
16
2020-01
South Maxwell Creek Road, Kinney Drive & Drainage Improvements (B&B)
17
2020-01A
Bunny Run Drive Culvert Replacements (2-48" Culverts) (BW2)
18
2020-02
Travis Farm Park - Phase II (Bid and Construction )
19
2020-03
Timbers Addition Drainage Channel Improvements (Bid and Construction) (N-S)
20
2020-04
Lonesome Dove Trail Drainage Culvert Extensions (Bid and Construction) (BW2)
21
2020-05
North Hill Park - Phase III (Bid and Construction)
22
Project #
Project NameProcurementFabricateInstall
23
2018-06
City Facilities - HVAC / Boiler / Chiller Upgrades
24
2018-08
City Facilities - Emergency Power Generators
25
2020-06
City Marquee Signs Upgrades