Task NameDurationStartFinishPredecessorsAssigned To% CompleteStatusComments
 Collaboration powered by Smartsheet   |   Report Abuse
1
-Caliburn Compute Production Readiness
100.25d09/30/1902/17/2057%
2
-MDC Readiness
90d09/30/1901/31/2077%
3
-Chiller Plant Controls Enhancement Options
90d09/30/1901/31/2090%
4
-Controls Options Analysis
7d09/30/1910/08/19100%
5
+Carrier Option
7d09/30/1910/08/19100%Chose Carrier iVue
8
+ALC Option
7d09/30/1910/08/19100%
11
Enhancement Selection and Funding
21d10/09/1911/06/195, 8100%
12
Final Specifications and Quote
2d11/07/1911/08/1911100%$35,800 + TruVue Display system
13
PO
5d11/11/1911/15/1912100%
14
Provisioning
8w11/18/1901/10/2013100%
15
Pre Installation Site Visit
1d12/18/1912/18/19100%Scheduled with Carrier
16
Acquire / Configure Controls Server
2w01/07/2001/20/20100%May add additional memory in future.
17
Delivery and Staging
15d01/13/2001/31/201435%
18
-MDC Infrastructure Monitoring
40d11/18/1901/10/2047%
19
Upgrade Network Infrastructure
25d11/18/1912/20/1975%Having network expanded to accommodate rack power and environmentals
20
Implement Security Controls
10d12/23/1901/03/201985%implementing ACL for CDUs, and completing enclosure physical security enhancements
21
Implement Rack Level Power Monitoring
20d12/16/1901/10/2019FS -5d20%need 24 ports for Rack PDUs for branch circuit monitoring; CAT-6 in place
22
Implement Rack Level Environment Monitoring
20d12/16/1901/10/2019FS -5d20%will be installing gateway (1 port) and 4 IPs for sensor groups
23
-Implementation
8.25d02/03/2002/13/200%
24
MDC Shutdown
2h02/03/2002/03/20170%Shut down all non essential services, excluding fire detection suppression and security (house planel)
25
Demolition
1d02/03/2002/04/20240%trace and remove / disable all Armstrong / ALC controls components
26
Installation
3d02/04/2002/07/20250%install new iVue controls sensor contrrollers; install TruVue display and server
27
Testing
2d02/07/2002/11/20260%conduct full systems unit and integration testing, including monitoring alerts and alarms
28
Commissioning
1d02/11/2002/12/20270%finalize system certification along with start up/shutdown procedures
29
MDC Restart
1d02/12/2002/13/20280%restart hosted services and confirm operational status
30
-Caliburn System Readiness
20d12/20/1901/16/200%For OARC prep work
31
Task One
20d12/20/1901/16/200%Placeholder One
32
Task Two
20d12/20/1901/16/200%Placeholder Two
33
-Configuration Performance Testing
3d02/12/2002/17/200%
34
Caliburn LinPack Testing
3d02/12/2002/17/20280%Conducting load test of system configuration
35
MDC Power and Cooling Stress Test
1d02/12/2002/13/2034SS0%Will monitor and trend power and cooling infrastructure performance and metering
36
Production Readiness
002/17/2002/17/2033, 30, 290%Caliburn / ELF available for user access